Construction site update
We are now halfway through our exciting building process and still expect to be ready to move in mid NOV 2025.
The main building parts are now in place: concrete floors and walls, roof, gates, ventilation, compresses air pipes, main cabling, and heating system.
The expansion of the canteen did start up last week, and the next step is to install the large traverse crane and the 5 swing cranes in the new assembly hall, and after that epoxy coat the complete floor area.
So far, the process has gone remarkably smoothly with only a few minor surprises along the way.